65 km
120 km/h design speed
6 railway bridges
8 overpasses, 4 pedestrian crossings
72 culverts, 6 agricultural crossings
106 utility crossings
The Osmanli-Imisli Railway Project covers the preparation of technical-economic feasibility studies, design, and bill of quantities documents for the reconstruction of the section of the existing line between km 1 and km 65. Within the scope of the project, improvement of the line geometry, renewal of the railway infrastructure and superstructure, and redesign of the stations are envisaged. The 5 stations to be redesigned are Mursalli, Saracalar, Saatli, Becar, and Imisli.
A design speed of up to 120 km/h has been adopted for the single-track railway with a 1,520 mm track gauge.
Within the scope of structures and crossings, 6 railway bridges with a total length of 393.85 m have been designed. For road crossings, 8 overpasses and 1 underpass have been designed; 4 pedestrian crossings are planned, comprising 2 pedestrian underpasses on the main line and one pedestrian overpass each at the Saatli and Imisli stations. In addition, 72 culverts (71 rectangular box-section and 1 circular-section) and 6 agricultural crossings have been designed. The project includes 13 level crossings, and 106 utility crossings are envisaged for the passage of infrastructure lines.
The modernization of the Osmanli - Imisli section will contribute to Azerbaijan's east-west transport connections by improving the operating conditions of the Osmanli - Imisli - Horadiz line.
The Osmanli-Imisli Railway Project covers the preparation of technical-economic feasibility studies, design, and bill of quantities documents for the reconstruction of the section of the existing line between km 1 and km 65. Within the scope of the project, improvement of the line geometry, renewal of the railway infrastructure and superstructure, and redesign of the stations are envisaged. The 5 stations to be redesigned are Mursalli, Saracalar, Saatli, Becar, and Imisli.
A design speed of up to 120 km/h has been adopted for the single-track railway with a 1,520 mm track gauge.
Within the scope of structures and crossings, 6 railway bridges with a total length of 393.85 m have been designed. For road crossings, 8 overpasses and 1 underpass have been designed; 4 pedestrian crossings are planned, comprising 2 pedestrian underpasses on the main line and one pedestrian overpass each at the Saatli and Imisli stations. In addition, 72 culverts (71 rectangular box-section and 1 circular-section) and 6 agricultural crossings have been designed. The project includes 13 level crossings, and 106 utility crossings are envisaged for the passage of infrastructure lines.
The modernization of the Osmanli - Imisli section will contribute to Azerbaijan's east-west transport connections by improving the operating conditions of the Osmanli - Imisli - Horadiz line.